Timeline

The chart below shows the timeline of the IMPACT project. The key elements are:

  • Realisation of the project during the ERI funding period 2025-2028.
  • Long shutdown of the HIPA accelerator and all its connected facilities for 16 months starting in January 2027.
  • Normal IMPACT user operation starting in May 2029.